Consultancy services related to the development of a technical solution for the connection of the future wind farm Rakova Bara to the power system of Serbia

Consultancy services related to the development of a technical solution for the connection of the future wind farm Rakova Bara to the power system of Serbia for the purposes of early public consultations and spatial planning development.

The grid connection consists of the following components:

  • 400kV OHL for connecting the new 400kV SWY Kučevo to the existing OHL no. 401 /2 SWY Drmno – HPP Djerdap 1 (LI/LO);
  • Development of a proposal for the location and orientation of the future 33/400kV SS Rakova Bara and 400kV SWY Kučevo;
  • Proposal of 400kV transmission line corridors and 33kV internal lines;

Services:

  • Technical assessment of project elements;
  • Selection of the optimal variant for the 33кV and 400kV overhead line route of line;
  • Selection of optimal location initial layout of future 400/33kV substation and 400kV switchyard;