The project comprises construction of the following grid infrastructure:
- SS 400/110kV Belgrade 50
- 2×400 kV transmission line SS Belgrade 50 – SWY Čibuk 1 with equipping of 400 kV bays at Chibuk 1 (approx 85km)
- Two 400 kV transmission lines for the lead-in of 400kV OHL no. 450 (SWY Mladost – SS Novi Sad 3) into SS Belgrade 50 (approx 24km)
- Two double-circuit 110 kV transmission lines for the lead-in of OHL no.104 /8 (TS Stara Pazova – SS Indjija 2) into SS Belgrade 50 (approx 25km)
- Two double-circuit 110 kV transmission lines for the lead-in of OHL no. 1178 AB (SS Beograd 5 – SS Belgrade 9) into SS Belgrade 50 (approx 14km)
- Two 110kV underground cables SS Belgrade 50 – SS Belgrade 49 (Airport) (approx 10km);
Services:
- Checking of technical and general documentation, including technical review of Design for Construction Permit in line with Serbian legislation;
- Support to the Client in project management;
- Project planning;
- Checking of obtained conditions and consents, and preparation of relevant review reports;
- Preparation of technical specifications and procurement documents;
Supervision of works on construction of new SS Belgrade 50.