Supervision of construction works on reconstruction of existing 110kV, 220kV and 400kV overhead transmission lines in Serbia

The construction works on reconstruction of  existing 110kV, 220kV and 400kV overhead transmission lines, in the crossing zone with future Highway E-763, Section 3, Obrenovac – Ub, commenced in January 2016. The project is related to a total of 8 lines, and the Contractors are Energomontaža Belgrade and Elektroistok Izgradnja Belgrade. The deadline for completion of the contract of the Contractors is 12 months.

E&E was selected by the Ministry for Construction, Traffic and Infrastructure to provide services of supervision of construction works. The E&E team consists of two electrical engineers and two civil engineers, all licensed for provision of contracted services.